| Project Schedule |
 |
|
This provides the existing schedule of work for the S.R. 51 – S.R. 88 Intersection Improvement Project. This schedule will be further updated and defined as the project progresses.
|
Timing |
Public Involvement |
Activity |
|
Early 2005 |
Obtain background information. Continue preliminary design of alternatives. Complete Phase 1 Preliminary Alternatives Study. |
|
|
Early 2005 |
Introduce the project. Present preliminary alternatives. Gather public opinions and concerns on the alternatives and their impacts. |
1st Public Meeting |
|
2005 - 2008 |
Select preferred alternative. Complete preliminary engineering. Receive environmental approval. Complete final design. Right-of-way acquisition/utility relocation. |
|
|
2008 |
Begin construction |
|
|
Late 2010 |
Complete construction |
|
|
|
|