Project Schedule
This provides the existing schedule of work for the S.R. 51 – S.R. 88 Intersection Improvement Project. This schedule will be further updated and defined as the project progresses.
 
Timing Public Involvement Activity

Early 2005

Obtain background information.
Continue preliminary design of alternatives.
Complete Phase 1 Preliminary Alternatives Study.
 
Early 2005 Introduce the project.
Present preliminary alternatives.
Gather public opinions and concerns on the alternatives and their impacts.
1st Public Meeting
2005 - 2008 Select preferred alternative.
Complete preliminary engineering.
Receive environmental approval.
Complete final design.
Right-of-way acquisition/utility relocation.
 
2008 Begin construction  
Late 2010 Complete construction  